Work Plan
9/20 Fri
Office equipment will be packed and disconnected by user, eSolia will help with IT devices.
All will be moved from 1F to 3F meeting room to be temporary stored.
9/21 Sat
eSolia will start remove old network cables and pull new cabling.
9/22 Sun
New carpet and walls, cabinets will be replaced on 1F.
No planned work for eSolia.
9/23 Mon
Desk furniture delivered and constructed.
eSolia will begin work after the installation of desk & furniture to pull LAN port under each desk.
Temporary stored away devices will be carried in and eSolia will connect PC / Monitors.
9/24 Tue
eSolia will stand by for on site user support & project follow-up in the morning.